Mozambique MECHANICAL MINE CLEARANCE TRIAL - FINAL REPORT
Commercial in Confidence United Nations Demining Programme Subject: MECHANICAL MINE CLEARANCE TRIAL - FINAL REPORT Introduction
1. The Krohn Demining System was introduced to Mozambique in August 1995. Development of procedures and
machines to the environment took place with support from the UN ADP. These develpments led to a field trial being
conducted at Sabie on 6 - 7 May 1996. The trial featured 264 live mines placed in a prepared area that was then
cleared by machine. The aim of the trial was to provide a quantifiable record of the performance of the Krohn Deming
System.
Test Minefield
It was hoped to use a greater range of mines reflecting all types found throughout Mozambique but they were not
available. However, the mines supplied are those most commonly found in Maputo Province. Commercial in Confidence |
Commercial in Confidence Tripwires were attached to each of the MUV 3 fuzes on the OZM 4's. These were deployed to ensure that the machine struck the mine first 6 times, the tripwire first 7 times and both simulanteously 5 times. The test area was designed to ensure that mines detonated individually for ease of recording and to be compact to reduce the amount of ground that needed to be cleared by hand. A plan of the test area is attached at Annex B and photographs are at Annex C. A cordon was maintained 300 metres from the mined area by the MMC team throughout the trial. It consisted of 30 locally employed guards and a series of stakes, tapes and warning signs. 6. Timings. The timings for the test were as follows:
Concept of MMC Operations 7. First Machine. The first machine is designed to detonate mines and clear trip wires and vegetation. It has a rotating steel tiller with tungsten teeth which covers a 3 metre wide strip of ground up to a depth of 50 cm. 8. Second Machine. The second machine is designed to disrupt or detonate any mines remaining, after the first machine process. It has two counter rotating steel tillers which "mulch" the soil and break up any large solid objects. It cannot however, break steel cased fragmentation mines. During normal operations the second and first machine work together in echelon formation however, for ease of recording detonations they operated individually during the trial. 9. Third Machine. The third machine is designed to bring any remaining Mines (particularly steel cased mines) to the surface for visual identification and subsequent disposal. It is a wheeled armoured tractor with a plough and a cabin capable of accommodating up to 6 "spotters". It also features a crane with an electromagnet device for moving steel cased mines. This machine is supported by hand deminers to conduct demolition's. Photographs of all the machines are attached at Annex D.
Method of Assessment 10. The trial was assessed using an observer inside the machines as they operated and an observer at the control point. The number of detonations was confirmed after each |
Commercial in Confidence machine completed a pass along the length of the test area. Two distinct types of detonation were heard, full detonation of main charge and detonators from the PMD 6 initiating outside the mine. Due to the construction of the PMD 6, in many instances detonators attached to fuze mechanisms fell out of the explosive charge as they passed thorough the machines. Accurate assessment of the results was not possible until after the ground had been cleared by hand and all mines were accounted for. Results were divided into four categories:
The status of cased explosive debris (category c.) was specified prior to the test in the letter attached at Annex E. Mines in category d. were assumed to have been completely disrupted with no identifiable fuze componants remaining. Due to the thoroughness of the hand clearance and the clarity with which detonations were heard this assumption is reasonable. Disruption is the process by which mines are broken up as opposed to detonation which refers to a mine functioning as designed. For the purposes of the trial a mine was considered completely disrupted if no cased explosive remained and partially disrupted if cased explosive was located after the mechanical clearance. Mechanical Processes 12. First Machine. The first machine used 6 overlapping passes to cover the test area, tilling the ground a depth of 300 mm. During this process which took 45 minutes of operating time 149 detonations were counted. The detailed results from the first machine process are attached at Annex F. It was also noted during this process that some PMD 6 mines had passed through the machine and remained completely intact. 13. Second Machine. The second machine used 10 overlapping passes to cover the test area twice. Durrng this process, which took a total of 1 hour 40 minutes, 19 detonations were counted. The detailed results of this process are attached at Annex G. The number of mines which were disrupted during this process was not known until the hand clearance of the area was complete. During this process one detonation occurred in panel 7 whilst the machine was in panel 12. This was probably the result of a MUV pin responding to a slight stimulus causing the striker to fire. Also, it was noted that at least two OZM 4's detonated under the machine in a buffer panel indicating that mines were moving from their original locations as a result of machine processes. |
On the final pass of the second machine three OZM 4's were spotted in panel 12. In an attempt to disrupt these mines the tiller was lowered and the machine reversed over the area. The OZM 4's remained intact and were not located by the third machine. Had the tiller been raised the mines would have remained on the surface and could easily have been located. 14. Third Machine. The third machine used a total of 30 passes to cover the test area six times. During this time one OZM 4 was recovered from panel 9 using the electromagnetic device and placed to the side of the test area for demolition. A partially disrupted PMN 2 was rnarked in panel 11 for subsequent demolition. The whole process took- around 3 hours. The OZM 4 was removed from the test area during the first pass, however, the PMN 2 was marked and remained in place until all passes were complete. Therefore, the area surrounding the PMN 2 was avoided by the machine. Had there been any other mines in this area they would not have been unearthed by the third machine. Hand Clearance 15. On completion of MMC operations the entire test area was searched by hand over a period of 6 working days. Thirty experienced deminers from the UN ADP were employed on this task. They used a combination of electronic instrument and manual excavation search techniques and shifted all the ground tilled by the machine (600 cubic metres). Photographs of the hand clearance are attached at Annex H. During this search the following items were located:
A detalled record of iterns located by the hand clearance operation is attached at Annex I. Photographs of the debris are attached at Annex J.
16. The results of the MMC trial are shown below: Detonated:
4 |
Found by third machine:
The 94 mines not detonated or located by the third machine were accounted for as follows: Partially disrupted:
Completely disrupted:
17. The test achieved its aim by providing a quantifiable record of the performance of the rnachines. All of the mines were either detonated or disrupted to various degrees. However, 38 items of cased explosives remained uncleared including four OZM4's with fuzes sheared off.
Mike Croll Annexes: A Photograph of test area 5 |
Annex A to Photographs of Test Site
General area view
Close up of ground showing mines being laid
|
Annex B to MMC Test Minefield Layout |
Annex C to Test area showing marking stakes PMN mines in panel 2
|
Annex D to Photographs of Machines
|
Appendix 1 to Photographs of Machines
|
Annex E to Commercial in Confidence SAFETY CRITERIA FOR
1. The following criteria are to be applied for the duration of the ADP-coordinated trial for the Krohn system
mechanical mine clearance machines. These safety criteria relate to the debris remaining after the machines have
passed through the minefield and completed all of the required passes. These are the minimum safety standards.
All debris is to be checked
Any debris which consists of explosive still contained in its casing is to be regarded as UNSAFE and it is not be
handled. It must be destroyed in situ using approved explosive disposal methods.
Any debris which consists of the fuzing system which has not functioned as intended is to be regarded as UNSAFE
and it is not be handled. It must be destroyed in situ using approved explosive disposal methods.
Any debris which consists of the top plate or percussion cap is to be regarded as UNSAFE and it is not to be
handled. It must be destroyed in situ using approved explosive disposal methods.
Any debris which consists of an empty mine casing, that is, that it does not contain any explosive or explosive
components is to be regarded as SAFE and may be handled and cleared from the minefield.
Authorised By: Date: 4 May 1996
G. P. LINDSTROM
Commercial in Confidence |
Annex F to Record of First Machine Performance
|
Annex G to Record of Second Machine Performance
Number of mines detonated = 16.5% of total remaining Time required for 10 passes = 1 hour 40minutes |
Annex H to Photographs of Hand Clearance General view of hand clearance
Deminer at work. Note the excavation technique combined with electronic detector |
Annex I to Record of items found at the test site after MMC operations
Other items found
|
Annex J to Photographs of Debris OZM 4
MUZ fuzes with detonators attached |
Appendex 1 Photographs of Debris Explosive fragments from PMD 6
Mine Debris |
KMMCS - Maschinelle Minenräumung und Bodensanierung
(KMMCS - Mechanical Mine Clearance and Soil Rehabilitation)
Tobias Steidle
Am Ehrenhain 2
D-38678 Clausthal
Germany
Tel.: +49 (0) 5323 92 21 55
Fax: +49 (0) 5323 92 21 56
Mobil: +49 (0) 170 9988 170
E-Mail contact
Ideas and mistakes please report to
Webmaster